ATO Timeline
Project timeline: 2026-01-06 → 2026-09-15 (252 days)
Overall Timeline Progress
Day 30 of 252
Target ATO Date
2026-09-15
2026-01-0612% elapsed2026-09-15
Project Phases
Initiation & Scoping
2026-01-062026-02-07
Control Selection & Tailoring
2026-02-102026-03-14
Implementation & Evidence
2026-03-172026-06-1361%
SSP Documentation
2026-04-072026-07-0445%
3PAO Assessment
2026-07-072026-08-15
Remediation & Final Package
2026-08-182026-09-05
ATO Decision
2026-09-082026-09-15
Complete In Progress Planned Today
Key Milestones
Kickoff Complete
2026-01-10
Baseline Approved
2026-02-07
Controls 50% Implemented
2026-04-15
SSP Draft Complete
2026-06-01
3PAO Engaged
2026-07-07
SAR Delivered
2026-08-15
ATO Granted
2026-09-15